The Suffolk County Water Authority has picked its route for a new water main to the North Fork: under the Peconic River and east along Main Road through Riverhead. Now it has to get past Riverhead Town.
The authority's board adopted its environmental findings on Nov. 19, finishing its state environmental review and choosing Main Road over the original Sound Avenue route, RiverheadLOCAL and The Suffolk Times reported. The authority told The Suffolk Times it hopes to break ground in 2027, with about a year of construction once final permits are in hand.
What would be built
- A 24-inch main, about 7.2 miles long, from the Riverside-Flanders area, under the Peconic River near the Cross River Drive bridge, then east on Main Road to the authority's existing pipes in Laurel.
- One booster station on authority-owned land near the southeast corner of Cross River Drive and Main Road in Aquebogue.
- No hookups in Riverhead. The water goes to the authority's Southold system, not the Riverhead Water District.
Why it matters
The authority runs 60 wells in 18 well fields on the North Fork for about 9,500 customers, and says demand keeps rising. Most of those wells tap a shallow aquifer exposed to farm chemicals and rising salt levels. The review expects to take eight Southold wells out of regular service and cut pumping at nine others.
Main Road is about a mile shorter than Sound Avenue and needs only one booster station, but passes more driveways and businesses. A spokesman put its cost at about $25 million, versus $35 million for the Sound Avenue route, The Suffolk Times reported.
Drivers can expect delays. The findings call for daily online updates on work spots and detours, a construction manager, a traffic plan around Aquebogue Elementary School, and avoiding the busiest summer and fall stretches where practical.
"After a thorough, transparent environmental review shaped by public input, we are ready to move from planning to construction," board chairman Charlie Lefkowitz said in a statement.
The Riverhead fight
Riverhead's Town Board voted unanimously on Oct. 6 that the project needs local approvals, including a special permit for the booster station. The authority says it is exempt. Its February lawsuit over the town's earlier ruling is still in State Supreme Court, with evidence exchange due by Dec. 15, RiverheadLOCAL reported. The board OK'd more legal action on Oct. 29, but as of Nov. 23 had not filed it.
State highway and wetlands approvals and a federal permit for the river crossing are still pending, The South Shore Press reported.
Source check: November 29, 2026, about 7:30 AM ET. "Water authority wraps up NoFo water main review, OKs more legal action against Riverhead," RiverheadLOCAL, Nov. 24, 2026 (route, booster site, lawsuit status, Dec. 15 deadline); "SCWA eyes 2027 start for controversial North Fork pipeline," The Suffolk Times, Nov. 25, 2026 (2027 start, costs, wells, quote); The South Shore Press, Nov. 28, 2026 (pending permits); SCWA North Fork Water Main Project page (well counts, 2028 completion target, environmental documents).